BMS Building Project Blog: Week of July 28, 2019

Week of July 28, 2019: 

Week 76 - 

As we enter into the 76th week of construction, we can look forward to the following:

  • Phase 1

  • Continue to maintain sediment erosion control around the perimeter of the construction site.

  • A/E Punch List; Section C & D

  • Install Stage Flooring in Auditorium

  • Install Auditorium Equipment

  • Paint: Section A & B & C & D

  • Test Fire Alarm Devices

  • Install Access Control

  • Maintain Landscaping

  • Rooftop Unit Commissioning

  • Furniture Deliveries

  • Equipment Deliveries

  • Install Telephones

  • Install Classroom A/V

  • Noise level: Landscaping and Heavy Equipment Operators

  • Phase 2 Began June 24, 2019

  • Continue to maintain sediment erosion control around the perimeter of the construction site.

  • Remove Bituminous Roads

  • Demolition Process in Zone 1

  • Demolition Process in Zone 2

  • Demolition Process in Zone 3

  • Install Light Pole Bases

  • Temporary Construction Fence Installation

  • Tree Protection

  • Tree/Brush Removal

  • Noise level: Heavy Equipment Operators

BMS Eagle in our front foyer area! 

Art classroom looking amazing! 

Science classroom with lab tables in place! (we can see the old building through the windows!)

Media center shelves in place. Ready for books!